Bored pile work for radiology in Graz in full swing
On the grounds of the LKH University Hospital in Graz, the new building of the Univ. Radiology Clinic is being constructed over a period of nearly 4 years. After the preparatory measures, which were started in October 2022, the bored pile work for the up to 10 m deep excavation pit and the deep foundation is now in full swing.
About half of the new 5- to 7-story building complex is underground. This, together with the surrounding existing buildings, made it necessary to enclose the excavation pit, which is being realized in the form of a dissolved bored pile wall with anchors and steel stiffeners.
Civil engineering work is progressing rapidly. In addition to the construction pit enclosure, the first deep foundation piles have already been installed, and the first floor slab sections are to follow from the end of July. Overall completion is scheduled for mid-2026.
ARGE Moser Architects – Thomas Lorenz was commissioned with the general planning services for this project, while the team from Thomas Lorenz is responsible for the structural design.
Share this post:
Facebook
Twitter
LinkedIn
WhatsApp
E-Mail
More news
New Psychiatry Building at Salzburg University Hospital Opened
10. September 2026
New Construction Site Offices in Operation
4. September 2026
Presentation at the Advance Steel User Days 2025
12. September 2025
Hyundai Research Campus Rüsselsheim Operational
5. September 2025
“QUADRILL” Linz – last facade element lifted
29. August 2025
Klinik Favoriten – Construction Progress “ARIO”
22. August 2025
Company Holiday Week 33
8. August 2025
New Building Component M Ordensklinikum Linz Started!
25. July 2025












