Steel hood for a logistics hall
Combining steel and concrete in buildings is nothing new. But in the case of the high-bay warehouse of Fa. VOG AG in Linz, that was it.
The steel structure of the high-bay warehouse roof, weighing a total of 173 tonnes, was mounted on the precast reinforced concrete structure, which is up to 20 m high.
The profiles were optimised by the Thomas Lorenz team, the connections calculated and then the factory planning drawn up. The assembly could then be completed quickly in only 4 weeks by Metallica Stahl- und Fassadentechnik.
More news
New Psychiatry Building at Salzburg University Hospital Opened
10. September 2026
New Construction Site Offices in Operation
4. September 2026
Presentation at the Advance Steel User Days 2025
12. September 2025
Hyundai Research Campus Rüsselsheim Operational
5. September 2025
“QUADRILL” Linz – last facade element lifted
29. August 2025
Klinik Favoriten – Construction Progress “ARIO”
22. August 2025
Company Holiday Week 33
8. August 2025
New Building Component M Ordensklinikum Linz Started!
25. July 2025