AKH CTMT Vienna – Construction progress
Over the next few years, MedUni Vienna will establish three new research areas - including the "Center for Translational Medicine and Therapeutics", or "CTMT" for short - at the Vienna General Hospital site as part of the ongoing construction of an integrated MedUni campus. Here is information on the current construction progress.
The new building is designed as a reinforced concrete structure. The building area above the lecture hall is supported on level 9 with steel trusses and suspended with tension columns. The steel construction work is being carried out by METALLICA Stahl- und Fassadentechnik GmbH, with the work planning coming from the company of Thomas Lorenz. Moser Architects ZT GmbH is responsible for the architectural planning and Toms ZT GmbH is the structural engineer.
A total of approx. 435 tons of steel processed and installed and approx. 120 million euros were invested in the overall construction project. Completion is planned for 2025.
The steel, glass and façade construction department was allowed to visit the METALLICA plant in Weiz during the factory assembly of the individual truss components, which weigh up to almost 10 tons. Experiences were exchanged with the plant employees and some new insights into the plant’s internal processes were gained.
More news
New Psychiatry Building at Salzburg University Hospital Opened
10. September 2026
New Construction Site Offices in Operation
4. September 2026
Presentation at the Advance Steel User Days 2025
12. September 2025
Hyundai Research Campus Rüsselsheim Operational
5. September 2025
“QUADRILL” Linz – last facade element lifted
29. August 2025
Klinik Favoriten – Construction Progress “ARIO”
22. August 2025
Company Holiday Week 33
8. August 2025
New Building Component M Ordensklinikum Linz Started!
25. July 2025