New Working World AT&S – GU takes off in full swing

New Working World AT&S – GU takes off in full swing

The groundbreaking ceremony took place at the end of May, and one month later the first concrete is already flowing. This is possible because the planning was already created with BIM in 3D from the beginning.
Collisions could be recognized and eliminated early, changes quickly incorporated and all plans derived from the “digital twin”. The general contractor ÖSTU-Stettin / Strabag already had a large part of the plans available at the start of construction and it could start immediately after the demolition and the clearing of the construction site. Here are a few hard facts about the 4-story new construction complex:
  • 8,335 m² gross floor space
  • 4,400 m³ concrete
  • 535,000 kg reinforcing steel
  • 1.800 m² facade
In 18 weeks the tower cranes will already be dismantled again, by then the shell should already be finished. Commissioning is planned for the autumn of 2022. Congratulations to all involved and keep up the good work!
Share this post:
Facebook
Twitter
LinkedIn
WhatsApp
E-Mail

CONTACT
US NOW

We answer your questions quickly and reliably.

Offices:

Graz, Vienna

Contact:

Scroll to Top